UppSense 2016/2017

Company: UppSense 2017
Start: januari 27, 2017
Finish: september 7, 2017
Report Date: februari 7, 2017

Gantt Chart

WBS Name Work
     
1 Brainstorm 5d
2 Priliminary Design 10d
2.1 1st Feedback
2.2 Bank Account 1d
2.3 Contact Ove Öhman 1d
2.4 Make a Logo 1d
2.5 Giveaway Scifest Poll 1d
2.6 Call Fiomi 1d
2.7 Coaching Subscription 1d
2.8 SciFest 3d
2.8.1 SciFest Event
2.8.2 Giveaways 1d
2.8.3 Poster 1d
2.8.4 Eyecatcher 1d
2.9 Assay Ready
2.10 System Design
2.11 Transducer Ready
2.12 Sponsors Search 1d
2.13 Sponsors Ready
3 Realization 10d
3.1 HW Ready
3.2 HW Design 10d
3.3 SW Low Lv. Ready
3.4 SW High Lv. Ready
4 2nd Feedback Preparation 3d
5 2nd Feedback
6 3rd Feedback Preparation 3d
7 3rd Feedback
8 Buy Tickets 1d
9 Optimization &Event 22d
9.1 2nd Round PT 7d
9.2 Contest Preparation 7d
9.3 Holidays 8d
9.4 Contest Event
Week 5, 2017 Week 6, 2017 Week 7, 2017 Week 8, 2017 Week 9, 2017 Week 10, 2017 Week 11, 2017 Week 12, 2017 Week 13, 2017 Week 14, 2017 Week 15, 2017 Week 16, 2017 Week 17, 2017 Week 18, 2017 Week 19, 2017 Week 20, 2017 Week 21, 2017 Week 22, 2017 Week 23, 2017 Week 24, 2017 Week 25, 2017 Week 26, 2017 Week 27, 2017 Week 28, 2017 Week 29, 2017 Week 30, 2017 Week 31, 2017 Week 32, 2017 Week 33, 2017 Week 34, 2017 Week 35, 2017 Week 36, 2017
27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13
All[71]
Hanzhao, Linlin
Linlin
All
Rasmus
Max
Elmar
Rasmus
Hanzhao
Ruth
A Group
SYS Group
T Group
Max
SP Group
SP Group[71]
SP Group
SP Group
All
All
Ruth
All
All

Tasks

WBS Name Start Finish Work Complete Cost Assigned to Notes
1 Brainstorm Jan 27 Feb 6 5d 0% All[71] Consider all options. Contact companies and departments that can help. Get some advise. I suggest to see all parts related with the performance of a Biosensor and consider all parts from the beginning. “Formulating the design question” and consider possible Constraints.
2 Priliminary Design Feb 7 May 1 10d Plan the experimental steps. I hope we can split different tasks so everyone can participate in the experimental part from the beginning. After dividing tasks in work comissions each individual comission will be in charge to set the detailed experimental plan and present it to the rest of the team in the meeting.
2.1 1st Feedback Feb 7 Feb 7 First feedback moment. Short video conference with the SensUs organization. Focuses on meeting each other and the general planning, including the design steps and timeline of these steps.
2.2 Bank Account Feb 10 Feb 10 1d 0% Hanzhao, Linlin
2.3 Contact Ove Öhman Feb 17 Feb 17 1d 0% Linlin
2.4 Make a Logo Feb 17 Feb 17 1d 0% All
2.5 Giveaway Scifest Poll Feb 17 Feb 17 1d 0% Rasmus The poll will be made with polly and the poll result will be or- dered. The syntax is: /poll “When should we meet?” “10am” “11am”. Check google as well.
2.6 Call Fiomi Feb 17 Feb 17 1d 0% Max
2.7 Coaching Subscription Feb 17 Feb 17 1d 0% Elmar
2.8 SciFest Mar 8 Mar 10 3d
2.8.1 SciFest Event Mar 10 Mar 10
2.8.2 Giveaways Mar 8 Mar 8 1d 0% Rasmus Set brochures and T-shirts (or whatever we decide).
2.8.3 Poster Mar 8 Mar 8 1d 0% Hanzhao
2.8.4 Eyecatcher Mar 8 Mar 8 1d 0% Ruth
2.9 Assay Ready Apr 3 Apr 3 A Group
2.10 System Design Apr 3 Apr 3 SYS Group The main decisions should be made and there should be a set- tled overall systems design (Which essay will be used? Which Transducer? Which processors?).
2.11 Transducer Ready May 1 May 1 T Group
2.12 Sponsors Search Feb 7 Mar 3 1d 0%
2.13 Sponsors Ready Mar 3 Mar 3 Max
3 Realization May 8 Aug 7 10d
3.1 HW Ready Jun 5 Jun 5 SP Group
3.2 HW Design May 8 May 25 10d 0% SP Group[71]
3.3 SW Low Lv. Ready Jul 3 Jul 3 SP Group
3.4 SW High Lv. Ready Aug 7 Aug 7 SP Group
4 2nd Feedback Preparation Apr 4 Apr 6 3d 0% All
5 2nd Feedback Apr 7 Apr 7 Second feedback moment. Short video conference with the SensUs organization.
6 3rd Feedback Preparation Jun 12 Jun 14 3d 0% All
7 3rd Feedback Jun 15 Jun 15 Third feedback moment. Short video conference with the SensUs organization.
8 Buy Tickets Jun 1 Jun 1 1d 0% Ruth
9 Optimization &Event Aug 7 Sep 7 22d
9.1 2nd Round PT Aug 7 Aug 15 7d 0% All
9.2 Contest Preparation Aug 16 Aug 24 7d 0% All
9.3 Holidays Aug 25 Sep 5 8d 0%
9.4 Contest Event Sep 7 Sep 7

Resources

Name Short name Type Group Email Cost
A Group Work 0
All Work 0
Elmar Work 0
Faye Work Faye.Keller@gmx.de 0
Hanzhao Work 0
Linlin Work 0
Max Work 0
PM Group Work 0
PR Group Work 0
Rasmus Work 0
Ruth Work 0
SP Group Work 0
SYS Group Work 0
T Group Work 0